Polaris Intelligence
Polaris
Intelligence
About
Ctrl K
Sign in
© Polaris Intelligence 2026
PrivacyTermsAdmin

Dragonfly

retired
Technology DemonstrationLEOCOSPAR 1998-067XHLaunched 8/24/2025
Admin Edit
Mission & Launch
Launch Mission
Zarya
Launch Vehicle
Falcon 9
Launch Date
8/24/2025
Last Contact
12/22/2025
Orbit & Mass
Orbit Class
LEO
Altitude
410.5 km
Inclination
51.63 deg
Dry Mass
2 kg
Total Mass
2 kg
Payload Classification
Mission Type
Technology Demonstration
Payload Category
TECH
Payload Class
A
Organizations
Operator
Kyushu Institute of Technology
Manufacturer
Kyushu Institute of Technology
Registry
COSPAR ID
1998-067XH
Track
Mentions
144
All verified mentions of this spacecraft in source documents.
0.0-5.0
Actions

NASA is requesting $434,600,000 for Dragonfly in fiscal year 2025.

FinancialGeneralValue 4.0Apr 22, 2024NASA confirms Dragonfly mission despite doubled costs

NASA set the total mission lifecycle cost for Dragonfly at $3,350,000,000 as part of the confirmation review.

Page4of8
FinancialLegalGovernanceValue 4.0Apr 22, 2024NASA confirms Dragonfly mission despite doubled costs

NASA projected $355,500,000 for Dragonfly in its fiscal year 2024 budget request.

FinancialValue 4.0Apr 22, 2024NASA confirms Dragonfly mission despite doubled costs

NASA confirmed the Dragonfly rotorcraft mission to Saturn’s moon Titan with a total lifecycle cost of $3,350,000,000.

PlanFinancialValue 5.0Apr 18, 2024NASA Confirms Dragonfly Rotorcraft Mission to Saturn’s Moon Titan

The Dragonfly project was directed to replan multiple times due to funding constraints in fiscal years 2020 through 2022.

PlanFinancialValue 3.5Apr 18, 2024NASA Confirms Dragonfly Rotorcraft Mission to Saturn’s Moon Titan

An updated Dragonfly budget and schedule plan was conditionally approved in November 2023 pending the outcome of the fiscal year 2025 budget process.

PlanGovernanceValue 2.0Apr 18, 2024NASA Confirms Dragonfly Rotorcraft Mission to Saturn’s Moon Titan

Dragonfly Bus from Dragonfly Aerospace provides solar array peak power of 1500 W, orbit average power of 800 W, an available payload mass of up to 250 kg, and a payload volume of 1000 x 1000 x 1 m.

CapabilityValue 5.0Jan 3, 2024Top Satellite Bus and Platforms in 2023

The delay of the Dragonfly mission was attributed to uncertainties in potential budgets for planetary science in fiscal years 2024 and 2025.

FinancialPlanValue 4.0Dec 11, 2023Creating a Venus exploration program

Lori Glaze, director of NASA’s planetary science division, announced on November 28 that the launch of the Dragonfly mission to Titan is delayed by a year to mid-2028.

PlanGovernanceValue 4.0Dec 11, 2023Creating a Venus exploration program

The Dragonfly team conducted a mission re-plan based on expected 2023-10-01 funding and estimated a revised launch readiness date of 2028-07-01.

PlanFinancialValue 4.0Dec 4, 2023NASA Authorizes Dragonfly to Proceed with Final Mission Design Work

NASA will postpone formal confirmation of the Dragonfly mission’s total cost and schedule until mid-2024 following the release of the 2024-10-01 President’s Budget Request.

PlanFinancialValue 3.0Dec 4, 2023NASA Authorizes Dragonfly to Proceed with Final Mission Design Work

Budget uncertainty prompted NASA to delay formal confirmation of the Dragonfly mission to Titan in November 2023.

PlanValue 3.0Nov 30, 2023NASA warns of “very problematic” space technology budget cuts

NASA's Agency Program Management Council delayed the confirmation decision for Dragonfly until after the release of the agency’s fiscal year 2025 budget proposal.

FinancialPlanGovernanceValue 3.0Nov 28, 2023NASA postpones Dragonfly review, launch date

The fiscal year 2024 request for Dragonfly of $327,700,000 was 18% less than the mission received in 2023.

FinancialValue 4.0Nov 28, 2023NASA postpones Dragonfly review, launch date

NASA plans to reconvene consideration of Dragonfly at the Agency Program Management Council in spring 2024.

PlanGeneralValue 2.8Nov 28, 2023NASA postpones Dragonfly review, launch date

NASA postponed formal confirmation of the Dragonfly mission in November 2023.

PlanValue 3.0Nov 28, 2023NASA postpones Dragonfly review, launch date

The Senate appropriations report would direct NASA to spend $327,700,000 on Dragonfly in fiscal year 2024.

FinancialLegalValue 4.0Nov 28, 2023NASA postpones Dragonfly review, launch date

NASA requested $327,700,000 for the Dragonfly mission in fiscal year 2024.

FinancialPlanValue 4.2Nov 28, 2023NASA postpones Dragonfly review, launch date

NASA planned a Dragonfly launch in 2026 at the time of mission selection.

PlanValue 3.5Nov 28, 2023NASA postpones Dragonfly review, launch date

NASA delayed the Dragonfly launch in 2020 from 2026 to 2027 due to external budget pressures linked to the pandemic.

PlanFinancialValue 4.0Nov 28, 2023NASA postpones Dragonfly review, launch date