神舟二十三号
The Tianzhou-10 cargo included crew consumables such as food, water, and clothing for the Shenzhou-21, Shenzhou-23, and Shenzhou-24 crews.
The Pakistani astronaut mission to Tiangong is expected to launch on Shenzhou-24 and return to Earth on Shenzhou-23.
The Long March 2F/G launch vehicle for Shenzhou-24 arrived three months after the Long March 2F/G launch vehicle for Shenzhou-23.
The yearlong taikonaut will launch on Shenzhou-23 in late May or early June and return about a year later on Shenzhou-24.
Both Shenzhou-23 and Shenzhou-24 launch vehicles were delivered months ahead of their original schedules after Shenzhou-20 was struck by space debris late last year.
The Shenzhou-23 crewed rocket launch will take place in Jiuquan in late May.
A Pakistani visiting astronaut will fly to the Tiangong Space Station aboard Shenzhou-24 for a short-term stay and will return to Earth on Shenzhou-23.
A taikonaut from Shenzhou-23 will spend one year aboard the Tiangong Space Station and will return to Earth on Shenzhou-24.
One astronaut from the Shenzhou-23 crew will conduct a one-year stay experiment.
Both launch vehicle assembly building bays at Jiuquan are focused on Shenzhou-23 and Shenzhou-24 preparations.
Shenzhou-23, designated as a rotating backup mission, is currently located at the Jiuquan Satellite Launch Center.
Shenzhou 23 is now at the JSLC.
Shenzhou-23's CZ-2F launcher is expected to follow soon.
Deliveries of Shenzhou-23 and Shenzhou-24 spacecraft and their Long March 2F/G launch vehicles were moved up by six months to be available in case of an emergency requiring a new spacecraft.
The timeline for Long March 2F Y23 and Shenzhou-23 is expected to move to the left.
The Shenzhou-23 spacecraft has arrived at Jiuquan.
Shenzhou-23 spacecraft is at the Jiuquan Satellite Launch Center and is prepared to be on standby until its planned mission in April.
Shenzhou-23 has arrived at Jiuquan and will provide emergency backup to the crew currently aboard Tiangong.
The next vehicle stack for Long March 2F Y23 and Shenzhou-23 was originally planned for March 2026.
Shenzhou-23 is not expected to arrive at Jiuquan until January.