Polaris Intelligence
Polaris
Intelligence
About
Ctrl K
Sign in
© Polaris Intelligence 2026
PrivacyTermsAdmin

JWST

active
Science ExplorationcislunarCOSPAR 2021-130ALaunched 12/25/2021
Admin Edit
Mission & Launch
Launch Mission
JWST Mission
Launch Vehicle
Ariane 5ECA+
Launch Date
12/25/2021
Orbit & Mass
Orbit Class
cislunar
Altitude
524,157.5 km
Inclination
4.17 deg
Dry Mass
5,861 kg
Total Mass
6,161 kg
Payload Classification
Mission Type
Science Exploration
Payload Category
AST
Payload Class
C
Organizations
Operator
NASA Goddard Space Flight Center
Manufacturer
Northrop Grumman
Registry
COSPAR ID
2021-130A
UN Registration
ST/SG/SER.E/1041
Track
Mentions
115
All verified mentions of this spacecraft in source documents.
0.0-5.0
Actions

An independent review commissioned by NASA of JWST in 2018 recommended that NASA increase oversight of the Ariane 5 to the same level as the agency does for missions launching on U.S. vehicles.

LegalGeneralValue 3.5Jun 2, 2021JWST launch slips to November
Page5of6

A 10-week launch processing schedule beginning with JWST’s shipment from California to the launch site in French Guiana in late August supports a mid-November launch timeframe.

PlanGeneralValue 4.0Jun 2, 2021JWST launch slips to November

JWST project officials said final preparations of the spacecraft are proceeding in a way that should make it ready for shipment to French Guiana by late August to support an 2021-10-31 launch.

PlanGeneralValue 4.0May 12, 2021Ariane 5 issue could delay JWST

The JWST program worked with Arianespace to change air vents in the Ariane 5 payload fairing.

RelationshipsCapabilityValue 4.0Oct 20, 2020JWST remains on track for October 2021 launch

NASA has discussed the JWST delay with the European Space Agency, and the European Space Agency will launch JWST on an Ariane 5 rocket from French Guiana.

PlanValue 4.0Jul 16, 2020NASA delays JWST launch by seven months

NASA had not set a new launch date for JWST as of June 2020 and planned a schedule assessment for July 2020.

PlanValue 3.7Jun 10, 2020NASA confirms JWST will miss March 2021 launch date

NASA maintained optimism that JWST could still launch in 2021 on an Ariane 5 from French Guiana.

PlanValue 3.5Jun 10, 2020NASA confirms JWST will miss March 2021 launch date

NASA closed its field centers in March 2020 because of the coronavirus pandemic, causing personnel overseeing JWST integration and testing at a Northrop Grumman facility in Southern California to return home.

GeneralValue 2.0Jun 10, 2020NASA confirms JWST will miss March 2021 launch date

The JWST project resumed some work with reduced personnel and shifts starting 2020-03-25 through early April.

PlanGrowthValue 2.0Apr 2, 2020Limited work continues on JWST

JWST integration and testing activities at the Northrop Grumman facility were reduced from about 45–50 NASA personnel weekly to about 15 personnel.

PlanValue 3.0Apr 2, 2020Limited work continues on JWST

The JWST program performed an updated joint confidence level analysis of the mission’s cost and schedule in October 2019 that assessed a 12 percent confidence level for meeting the March 2021 launch readiness date.

PlanFinancialValue 4.0Jan 28, 2020GAO warns of more JWST delays

Using a 70 percent confidence level metric, the GAO report estimated the JWST launch would likely occur in July 2021, a delay of four months from March 2021.

PlanValue 3.0Jan 28, 2020GAO warns of more JWST delays

Greg Robinson, JWST program director at NASA Headquarters, and Scott Willoughby, vice president and JWST program manager at Northrop Grumman, believed the mission was on track to complete a final set of environmental and deployment tests and be shipped to the launch site at Kourou, French Guiana, by the end of 2020.

PlanGovernanceValue 3.8Jan 28, 2020GAO warns of more JWST delays

The JWST program planned to reassess its launch date in the spring of 2020 after completing significant technical tasks on the mission.

PlanValue 3.0Jan 28, 2020GAO warns of more JWST delays

The JWST spacecraft element successfully completed its final thermal vacuum test on 2019-05-30.

PlanCapabilityValue 4.0Jun 3, 2019JWST and SLS drive up cost and schedule growth on NASA programs

NASA's JWST program held 60 days of margin for integration and testing of the combined spacecraft bus and optical elements, three weeks of margin after the observatory arrives at the launch site, and four months of reserve held at NASA Headquarters.

PlanCapabilityValue 4.0Mar 27, 2019JWST review board raises schedule concerns

Thermal vacuum testing of the JWST spacecraft was expected to begin the week of the National Academies' Space Science Week meeting on 2019-03-26.

PlanValue 4.0Mar 27, 2019JWST review board raises schedule concerns

The GAO argued that conducting a JCL at the system integration review would allow the JWST project to update its assumptions of risk and uncertainty based on testing the separate spacecraft bus and optical elements prior to integration.

PlanCapabilityValue 3.2Mar 27, 2019JWST review board raises schedule concerns

Greg Robinson is the director of the JWST program at NASA Headquarters and NASA is working to implement the review board recommendation for increased oversight of the Ariane 5 launch.

GovernanceGeneralValue 3.0Nov 1, 2018Independent board chair calls JWST a “step too far”

Work on JWST is following a revised schedule announced in June that calls for a launch at the end of March 2021.

PlanValue 4.0Nov 1, 2018Independent board chair calls JWST a “step too far”